March 3, 2012

Weekend after weekend, volunteers come from far and near to join in our project. What a blessing!






We have been blessed with decent weather lately, so the front entryway pad has been built and the window wells put in place to aid with site drainage.

The front door installation will begin after the completion of the concrete pad.

 The drywall installation continues during the week, with the mudding to begin this week. Most of the upper level is drywalled, and the vapor barrier is being installed in the basement.


Today, many hands (and backs!) aided in digging the trenches in the basement floor for the sump line. Messy, wet work...but they were rewarded with a delicious lunch! Thanks again ladies for working in the kitchen too!







Bucket by bucket, filling concrete bins. This is our third at least (or maybe fourth) concrete bin!  Many many buckets-worth...thanks especially to our young men!







The benches are now all beautifully stained, 
but the sanctuary was sealed off from the dust from the concrete work. 
Pictures will hopefully follow this week! 