Wednesday, 2 May 2012

April progress



Pulpit framing in progress, with baptismal in place, but not installed.

Tile in Kitchen.

Tile in washrooms is complete.















Sanctuary lighting installed.



Foam for benches is delivered.




Sanctuary lights are hung in place.

Foyer is now completed with the drywall, ready for priming.




Thursday, 5 April 2012

April 7th- Resting from our labours

This long weekend, there will be no work at the church. 
This is the first weekend off since Nov. 4th, so it is a much need rest for the laborers. 

May this weekend also be a time of reflection and remembrance of the real purpose for everything we do in life. Remembering our Lord's great sacrifice, and miracle of resurrection makes each day worth living. With out this gift of salvation, everything would be in vain, even this church project.

May God bless each and every one of our faithful supporters.

Saturday, 31 March 2012

March 31st


Help from Kitchener arrived early this morning to begin framing the pulpit area, and digging the trench for the upgraded water service. It is exciting to see the sanctuary taking shape. That is the most complete area so far. The walls are ready to be primed and painted. The baptismal should arrive this week, and then the pulpit area can be finished...if the HVAC permit is granted, inspected and approved this week. Please pray!