Monday, 30 January 2012

January 28th


Sanctuary Windows are in (except a few small ones) and they look very nice! It's hard to tell, since the air is filled with dust...thanks to the bench sanding!
Basement windows are also mostly installed. It changes the light, with out those red metal screens!



All the walls on the sanctuary level are being insulated now. The sound is already noticeably less! What a difference it will make to have drywall and insulation instead of the exposed block walls!



Volunteers from far and near are still willing to come help!
We are so appreciative of the support and love we have been shown thus far in our project.
The pulpit wall stone is complete.


Check back for updates! Now is when the visible progress will begin to happen.

It is a blessing to see the project take shape like this...and be reminded that just as building this house of God has taken many hands and many hours, the body of Christ is built with labours of love and, many different kinds of willing individuals.

Friday, 27 January 2012

Mid-week progress!!

Thanks to a few hard workers that came during the last 2 weeks...we went from this:


To this:
(We'll take better pictures tomorrow with the scaffolding out of the way... 
but I was too excited to wait!)

And the windows are being installed, should be done by next Wednesday! 
What a difference that will make!



Tomorrow's work will be concrete work for the ducting, sanding benches, 
and more wiring down stairs at least.

Join us on Sunday at 274 for our Farewell, or Feb. 5th for the last area sing in our old church...
Lord willing, by the next time our turn rolls around, we'll be able to host everyone in our new church! Singing will be wonderful!!! Praise God!

Wednesday, 25 January 2012

January 21, 2012



The stone behind the pulpit area is going up with the help and expertise from Ohio and Kitchener!

 Electrical work continues, along with HVAC planning.