Friday brought a few more volunteers from Ohio. Many thanks to those who come from so far to help.
The beams arrived, and were installed. We are still waiting on the 12 ft beam we needed most....but we were still able to accomplish other jobs.
Monday, 2 January 2012
Thursday, 29 December 2011
12/29/11 Progress
The sky jack arrived today, so they are able to finish the strapping and studding at the peak.
The washroom walls are all out now, and the beams will be installed tomorrow, Lord willing. It really opens up the space!
The opening that had been made by the previous church (which was completely unsupported!) has been beautifully replaced in by a volunteer all the way from Ohio!
Even our young men are spending their break from school helping haul dirt and concrete!
Wednesday, 28 December 2011
Progress
The change rooms/meeting rooms are framed in...



The washroom walls are down, floor broken, trench dug (almost all the way). Still waiting on the steel beams to finish the washroom area demolition.
Ducts down. Pile of dirt waiting to be hauled outside. Old wiring being removed.
New doorway between Kitchen and Pantry areas.
Right side change room, getting ready for wall beside stairwell.
We are thankful to the volunteers (about 20 a day so far this week) for taking time from their own holiday time off to come work with us.
We anticipate the beams coming for Friday's work. That would allow us to continue in the washroom renovation & start the Barrier Free washroom upstairs.
More pictures HERE

Ducts down. Pile of dirt waiting to be hauled outside. Old wiring being removed.
Right side change room, getting ready for wall beside stairwell.
We are thankful to the volunteers (about 20 a day so far this week) for taking time from their own holiday time off to come work with us.
We anticipate the beams coming for Friday's work. That would allow us to continue in the washroom renovation & start the Barrier Free washroom upstairs.
More pictures HERE